單項(xiàng)選擇題

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.


你可能感興趣的試題

3.單項(xiàng)選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement
B.project requirement
C.project charter
D.product specification

4.單項(xiàng)選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

6.單項(xiàng)選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

8.單項(xiàng)選擇題The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.project charter

9.單項(xiàng)選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

最新試題

The()provides the project manager with the authority to apply organizational resources to project activities.

題型:?jiǎn)雾?xiàng)選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

題型:?jiǎn)雾?xiàng)選擇題

() is one of the quality planning outputs.

題型:?jiǎn)雾?xiàng)選擇題

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

題型:?jiǎn)雾?xiàng)選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:?jiǎn)雾?xiàng)選擇題

Which of the following statement related to PMO is not correct?()

題型:?jiǎn)雾?xiàng)選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:?jiǎn)雾?xiàng)選擇題

空白(2)處應(yīng)選擇()

題型:?jiǎn)雾?xiàng)選擇題

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

題型:?jiǎn)雾?xiàng)選擇題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:?jiǎn)雾?xiàng)選擇題