()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value B.Earned value C.Actual cost D.Cost variance
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating B.defining C.planning D.sequencing