A.project management plan
B.contract
C.project human resource plan
D.project charter
您可能感興趣的試卷
你可能感興趣的試題
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders
The() defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
()means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure
() is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
最新試題
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
The()provides the project manager with the authority to apply organizational resources to project activities.
() is one of the quality planning outputs.
The() defines the phases that connect the beginning of a project to its end.
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
()means that every project has a definite beginning and a definite end.
The inputs of developing project management plan do not include()