On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating
B.cost estimating
C.project planning
D.schedule development


你可能感興趣的試題

最新試題

The inputs of developing project management plan do not include()

題型:單項選擇題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:單項選擇題

In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .

題型:單項選擇題

Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()

題型:單項選擇題

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

題型:單項選擇題

The() defines the phases that connect the beginning of a project to its end.

題型:單項選擇題

空白(1)處應選擇()

題型:單項選擇題

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

題型:單項選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:單項選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

題型:單項選擇題